
JBC of Wyoming Corp. v. City of Cheyenne
1992 WY 181
843 P.2d 1190
Case Number: 92-32
Decided: 12/21/1992
Supreme Court of Wyoming
JBC OF
WYOMING CORP., a corporation, Appellant (Plaintiff),
v.
CITY OF
Appeal from
District Court,
Bruce A.
Dunham
(argued), and Roxanne Jensen of Morrison & Foerster, Denver, CO, for appellant.
J. Kent
Rutledge (argued), of Lathrop & Rutledge,
Before MACY, C.J., and THOMAS, CARDINE,
URBIGKIT* and GOLDEN, JJ.
* Chief
Justice at time of oral argument.
CARDINE,
Justice.
[¶1.] An arbitrator awarded
JBC consequential damages equal to thirty percent (30%) per year of the unpaid
amounts due JBC in its contractual dispute with the
[¶2.] Because the arbitrator
abused his discretion in making this consequential damage award, we affirm the
trial court's order.
[¶3.] JBC states the issue
before us as follows:
Did the
district court err when it found that the neutral arbitrator exceeded his
authority by awarding compensatory damages for appellees' failure to pay monies
owed to appellant?
[¶4.] This action arises out
of the construction of the Stage II Little Snake Diversion Pipeline Project
(Project) near Encampment,
[¶5.] As the Project
proceeded, problems developed with one of JBC's subcontractors, Varra Companies,
Inc. (Varra). JBC brought suit against Varra after Varra allegedly "walked off
the job." This suit eventually expanded to include numerous other issues and to
engulf JBC, Varra, the Board, Banner Associates (the architect on the Project),
and various surety companies in costly litigation in state and federal courts,
which lasted until a settlement was reached on the eve of trial. As part of the
settlement process, and in view of their painful and expensive experience with
the court system, JBC and the appellees entered into an agreement to submit any
remaining and future contractual disputes between them to binding
arbitration.
[¶6.] The Submission
Agreement required the appellees and JBC each to appoint a representative with
full settlement authority. If the representatives failed to agree on any issue,
they were to appoint a neutral third party to decide it. Subsequent to execution
of the Submission Agreement, numerous problems in addition to those already in
controversy arose with the Project. The most serious of these concerned the 66-
and 72-inch pipe installed below ground at the Project site. The pipe had become
defective, and repairs estimated at over $4.5 million were
needed.
[¶7.] On July 10, 1987, JBC
filed suit in state district court against the City, the Board, and other named
defendants, seeking damages for the pipe design failures, structural embankment
failures, water quality problems, and payment of retainage due from the City and
Board under the contract. The complaint stated claims in both tort and contract.
The City and the Board responded with a motion to dismiss and application for
order of arbitration. On October 20, 1987, the trial court determined that JBC's
claims against the City and the Board were subject to the previously-executed
Submission Agreement. It stayed the suit as to the City and Board and ordered
JBC to submit its claims against them to arbitration under the
Agreement.
[¶8.] Meanwhile, by the end
of August 1987, the Board had suspended progress payments under the contract to
JBC. The Board claimed this suspension was justified under its contractual right
to "nullify" previous payments because of the construction defects. On September
4, 1987, JBC responded by notifying the Board that it was terminating the
contract for nonpayment. After this notice of termination, JBC proceeded to
complete the Project at its own expense.
[¶9.] On October 28, 1987,
JBC sent the Board a list of claims it intended to submit to the arbitration
process. These claims were divided into two categories: "Alternate A" and
"Alternate B." Alternate A was a total cost claim under the contract for the
expenses of the work plus a reasonable profit. JBC estimated the amount due
under Alternate A at $14.5 million. Alternate B consisted of a number of
individual claims totalling $8.25 million.
[¶10.] JBC initially presented a number of the
individual claims under Alternate B for resolution through the arbitration
process, and some of them were resolved. However, JBC became dissatisfied with
the Board's nonpayment of these claims after resolution and with its continued
withholding of nullification payments, so on March 3, 1989, JBC presented its
"total cost claim" for $19,895,133.00 to Warren Hunter, the neutral arbitrator.
The claim was based on a provision of the contract which allowed the contractor,
in the event of nonpayment, to terminate the agreement and to receive payment
for "all work executed and any expense sustained plus a reasonable profit." In a
footnote to its claim, JBC stated: "If this claim is granted and total cost
awarded, it will cover and dispose of all JBC's other
claims."
[¶11.] On May 18, 1989, Hunter ruled that JBC
was not entitled to exercise the total cost remedy provided for in the parties'
contract. However, because of the "serious effects" of the Owner's withholding
of funds from JBC, Hunter ruled that:
A. The
Owner must pay JBC an additional 30% per year (over and above the interest
allowed in Paragraph 101.16.04) on all funds found to have been improperly
withheld from the Contractor. This ruling will also apply to any funds not
promptly paid the Contractor because of the Owner's purported budgetary
problems. The additional dollar amount will be calculated starting on the date
the monies were originally due and continue until paid in
full.
B. JBC
retains the right to pursue any or all of their claims that have not been
settled.
[¶12.] In a letter to the parties dated June 28,
1989, Hunter further explained this award as follows:
2. Even
though I did not feel JBC was entitled to the complete Total Cost Claim * * *, I
did feel they were entitled to compensatory damages for the effects on their
company that resulted from the monies wrongfully withheld by the Board. My
reasoning for this was explained throughout the decision.
3. The 30%
is not interest. It is just the
method I chose to determine the compensatory damages.
4. The 30%
was awarded as fair and equitable compensatory damages to JBC for the damages
they suffered because of the Board wrongfully withholding payments due JBC.
Because I did not have, nor would the total information be available until all
claims were settled, all of the information needed to determine a fixed amount
for compensatory damages, I chose the percentage method because it could easily
be applied to the present known monies and also to any future monies that may
apply. [emphasis in original]
[¶13.] The City and Board moved the trial court
for an order correcting or vacating Hunter's award of 30% compensatory damages.
They also moved to disqualify Hunter as the neutral arbitrator, on the grounds
that he was biased toward JBC. Angered by their suggestion of bias, Hunter
resigned as the neutral arbitrator on July 16, 1989. The trial court entered an
order holding the motion to correct the award in abeyance. It appointed a new
arbitrator, Stuart Bartholomew, to hear JBC's remaining individual
claims.
[¶14.] After JBC's substantive claims were heard
and decided, and only the interest amount remained to be considered, JBC
petitioned the court, with extensive briefs and exhibits, to confirm the 30%
compensatory damage award and to remand for a calculation of damages. The
defendants responded by opposing this motion and again moving that the 30%
arbitration award be vacated. On December 19, 1991, the trial court ruled that
Hunter exceeded his authority in making the 30% award. It vacated the award.
After the trial court certified that there was no just cause for delay pursuant
to W.R.C.P. 54(b), JBC took timely appeal to this court from the trial court's
order vacating the arbitrator's award.
Standard of
Review
[¶15.] We have located no cases setting out the
standard of review to be followed when evaluating an order of the trial court
which vacates an arbitration award. Our prior cases do not make clear whether we
owe any deference to the trial court's determination that grounds existed for
vacating the award.
[¶16.] The trial court's power to set aside an
arbitration award seems best analogized for standard of review purposes to its
power to grant judgment notwithstanding a jury's verdict (JNOV). See W.R.C.P.
50(b). When reviewing the trial court's entry of a JNOV, we "undertake a full
review of the record without deference to the views of the trial court."
Inter-Mountain Threading, Inc. v. Baker Hughes Tubular Serv., Inc., 812 P.2d
555, 558 (
[¶17.] In reviewing the record below, we are
mindful that the grounds for vacating or modifying an arbitrator's award remain
narrow in scope. Because of its voluntary, informal nature, awards made in
arbitration are subject to less intensive scrutiny than are, for example, the
orders of administrative agencies. See W.S. 16-3-114. The reviewing court must
observe the principle that arbitrators are free to fashion forms of relief which
could not be ordered by a court in law or equity. W.S. 1-36-114(a)(v).
Furthermore, we are reluctant to disturb an arbitrator's just solution to a
controversy, even if it differs from the resolution we might have chosen, had we
been in the arbitrator's place. See Matter of Town of
Did the
Arbitrator Exceed His Authority?
[¶18.] Wyoming Statute 1-36-114(a) requires the
trial court upon application to vacate an arbitrator's award
where:
(i) The
award was procured by corruption, fraud or other undue
means;
(ii) There
was evident partiality by an arbitrator appointed as a neutral, corruption of
any of the arbitrators or misconduct prejudicing the rights of any
party;
(iii) The arbitrators exceeded their
powers;
(iv) The
arbitrators refused to postpone the hearing upon sufficient cause being shown,
refused to hear evidence material to the controversy or otherwise conducted the
hearing as to prejudice substantially the rights of a party;
or
(v) There
was no arbitration agreement, the issue was not adversely determined by a court
as provided by law and the applicant did not participate in the arbitration
hearing without raising the objection. The fact that the relief was such that it
could not or would not be granted by a court of law or equity is not a ground
for vacating or refusing to confirm the award. [emphasis
added]
[¶19.] When considering a motion to vacate, the
trial court is not limited to the grounds listed in the statute but may also
vacate the award for, among other reasons, "fraud, corruption, behavior beyond
the bounds of natural justice, excess of authority, or a manifest mistake of
fact or law appearing upon the face of the award." Texas West Oil and Gas Corp.
v. Fitzgerald, 726 P.2d 1056, 1062 (
a. Double
Recovery
[¶20.] The trial court found that if the 30%
compensatory damage award were allowed to stand in addition to recovery for the
individual claims, JBC would receive a double recovery. The consequential damage
award was a substitute for the total cost claim, which in turn was an
alternative remedy to JBC's individual claims. JBC had already submitted and
received payment for many of these individual claims. Since JBC is not entitled
to double recovery for its injuries, the trial court held that the consequential
damage award must be reversed.
[¶21.] Consequential damages, of course, are not
necessarily double recovery when awarded for foreseeable harm which differs from
that compensated by direct damages. The damages awarded in an action for breach
of contract are designed to put the plaintiff in the same position as if the
contract had been performed, less proper deductions. Robert W. Anderson
Housewrecking and Excavating, Inc. v. Board of Trustees, Sch. Dist. No. 25, 681
P.2d 1326, 1333 (
Subject to
the limitations stated in §§ 350-53, the injured party has a right to damages
based on his expectation interest as measured by
(a) the
loss in the value to him of the other party's performance caused by its failure
or deficiency, plus
(b) any other loss, including incidental or
consequential loss, caused by the breach, less
(c) any
cost or other loss that he has avoided by not having to perform. [emphasis
added]
[¶22.] Arbitrator Hunter's award was intended to
cover such "incidental or consequential loss," as demonstrated in the following
statement from his decision letter:
Under our
contracting system the Contractor is willing to take on considerable risk and
expend their resources for basically one reason - PAYMENT FOR WORK PERFORMED. To
withhold payment strikes at the very heart of the Owner's responsibility under
the contract. The contract specifications are very explicit in outlining the
payment requirements of the Owner. Withholding payment places a tremendous
hardship on the Contractor. The restriction of "cash flow" on any one project,
not only affects that project but normally sets off a type of "chain reaction"
that totally affects and encompasses the Contractor's entire company. As pointed
out in JBC's presentation, "As a result of the Board's failure to pay over one
year's worth of work, JBC's capital was impaired; its line of credit was reduced
from 16 million to 11 million; it didn't have resources to bid some jobs; its
overall backlog had to be reduced; its lenders increased its interest note by
1/2 of 1%; it suffered a reduction in its bonding capacity and had to obtain a
new bonding company." Because of the severe and far-reaching consequences of
withholding payment, the Engineer and Owner must, therefore, also bear the
tremendous responsibility and liability for the repercussions of their
action.
[¶23.] Thus, the prohibition on double recovery
did not necessarily prohibit JBC from recovering consequential damages in
addition to its direct damages.1 As will be
discussed, the real problem with the arbitrator's award lies in the fact that
JBC never made a claim for consequential damages under the claims submission
process.
b. JBC's
Failure to Present a Claim
[¶24.] The broad freedom an arbitrator has to
resolve disputes and fashion remedies is limited by the contractual nature of
the arbitration agreement from which he draws his powers.
The right
to have a dispute submitted to arbitration is contractual. Panhandle Eastern
Pipeline Company v. Smith,
T & M
Properties, 661 P.2d at 1044.
[¶25.] The Submission Agreement for arbitration
entered into by the parties required them to:
"submit to
the representatives, with copies to each other * * * a full statement of each
claim made by that party with respect to the Contract, along with such
documentary supporting material as that party considers
appropriate."
[¶26.] The representatives were to attempt to
resolve the parties' claims. If they could not do so, they were to select a
neutral third party to decide them. Thus, the submission agreement provided that
the arbitrator would decide only those claims made with respect to the contract
which were first submitted to the parties' representatives and then forwarded to
him for decision.
[¶27.] JBC's failure to submit a claim for
consequential damages was consistent with its position below that the total cost
remedy was the only contractual remedy provided to make JBC whole under the
circumstances. Since JBC never submitted a consequential damage claim according
to the required process, it seems almost self-evident that the arbitrator could
not make an award of consequential damages.
[¶28.] JBC now argues, however, that its failure
to submit a claim for consequential damages would not prevent the arbitrator
from making the award he did. JBC points us to cases holding that an arbitrator
is free to fashion relief additional to or different from that requested by the
parties, and that the questions submitted for the arbitrator's decision should
be broadly construed. Matter of Town of Greybull, supra 560 P.2d 1172;
Department of Public Safety v. Public Safety Employees Ass'n, 732 P.2d 1090
(Alaska 1987); Carte Blanche (Singapore) Pte., Ltd. v. Carte Blanche Int'l,
Ltd., 888 F.2d 260 (2nd Cir. 1989); National Tea Co. v. Richmond, 548 So.2d 930
(La. 1989); David Co. v. Jim W. Miller Const., Inc., 444 N.W.2d 836 (Minn.
1989); City of Worcester v. Granger Bros., Inc., 19 Mass. App. Ct. 379, 474
N.E.2d 1151 (1985), review denied 394 Mass. 1103, 477 N.E.2d 595 (1985); Seppala
& Aho-Spear Assoc. v. Westbrook Gardens, 388 A.2d 88 (Me.
1978).
[¶29.] Most of the cases JBC cites serve only to
cloud the real issue, which is whether JBC observed the contractually-mandated
requirements of the claims procedure. Carte Blanche, 888 F.2d 260, is closest on
point, in that it allowed the arbitrator to award relief for a claim which
should have been but was not properly filed. In that case the Eighth Circuit
held that the statement of issues provided by the parties was sufficiently broad
that it included the omitted claim. The terms of the submission agreement here
cannot be so easily satisfied. The total cost claim could not substitute, as JBC
argues, for a claim for consequential damages for failure to make timely
payment. A "claim" must be specific enough to connote assertion of a legal
right. Stephan & Sons, Inc. v.
Consequential
Damages in Tort
[¶30.] Because suggested as an issue on appeal,
we find it appropriate to discuss whether JBC can recover in tort for consequential damages resulting
from the City and Board's failure to pay. The issue may surface as the trial
court considers the remaining claims on remand, particularly JBC's tort claims,
which were not subject to arbitration under the Submission
Agreement.
[¶31.] We have recognized that breach by a
contracting party of an independent duty which arises out of the contractual
relationship may give rise to an action in tort. McCullough v. Golden Rule Ins.
Co., 789 P.2d 855 (
[¶32.] This is not to say that JBC has no
independent cause of action based in tort, only that such an action cannot be
based upon the fact that the City and Board failed to make timely payment. Our
holding on this point seems almost self-evident. Failure to pay sums due under a
contract or under arbitration provided for by contract is clearly ex contractu
rather than ex delicto.
Conclusion
[¶33.] We are not unsympathetic to the quandary
JBC found itself in when the City was either unwilling or unable to pay amounts
due under the contract and awarded in arbitration. However, we cannot allow JBC
to exempt itself from the claims procedure it agreed to in the Submission
Agreement, particularly where the failure to file a claim meant that the City
and Board would have insufficient notice that the question of moneys due as
consequential damages for nonpayment would be at issue. Since no claim for
consequential damages was made, the arbitrator had no authority to award such
damages. He exceeded his authority when he made the award. Therefore, the trial
court properly vacated this portion of the award.
[¶34.] Affirmed.
THOMAS and
URBIGKIT, JJ., each
files a separate specially concurring opinion.
FOOTNOTES
1 It is at least
questionable whether a claim for consequential damages could have been made
"with respect to the contract." JBC has not directed us to any provision of the
contract which allows for consequential damages of the type the arbitrator
ordered. At least one other court acting under similar circumstances denied
damages for delay ordered by an arbitrator which were not provided for by the
construction contract. See Harrison F. Blades, Inc. v. Jarman Memorial Hosp.
Bldg. Fund, Inc., 109
THOMAS, Justice,
concurring specially.
[¶35.] I am in accord with the decision of the
majority to affirm the order of the trial court reversing the award of
consequential damages by the arbitrator. I agree the arbitrator exceeded his
powers in this situation. My concern is about the portion of the opinion of the
majority that addresses consequential damages in tort. I do not find that the
issue of consequential damages in tort is properly before this court, and our
response to the arguments of the parties on the issue is clearly an advisory
opinion. I cannot join in that portion of the majority
opinion.
[¶36.] In introducing the topic the majority
states:
Because suggested as
an issue on appeal, we find it appropriate to discuss whether JBC can recover
in tort for consequential damages
resulting from the City and Board's failure to pay. The issue may surface as the
trial court considers the remaining claims on remand, particularly JBC's tort
claims, which were not subject to arbitration under the Submission
Agreement.
Majority
opinion at 1197.
The order
that is before the court in this case dealt only with rulings of the arbitrator
and, by definition of the majority, these tort claims were not subject to
arbitration. This portion of the majority opinion deals gratuitously with a
question that is not presented to the court.
To answer questions
which were not brought before this Court would be to issue an advisory opinion.
In State Board of Equalization v. Jackson Hole Ski Corporation, Wyo., 745 P.2d
58, 59 (1987), we said:
"Although the question
as postulated in this case may be properly before us in the future, to render an
opinion here would be to issue an advisory opinion. This court has said
repeatedly that it will not issue advisory opinions, and we decline to do so
now. Graham v.
Brad Ragan
Tire Co. v. Gearhart Industries, 744 P.2d 1125, 1126 (
[¶37.] Our rule is that this court does not
offer advisory opinions. Briggs v. Wyoming Nat'l Bank, 836 P.2d 263 (Wyo. 1992);
Phillips v. Duro-Last Roofing, Inc., 806 P.2d 834 (Wyo. 1991); Coulthard v.
Cossairt, 803 P.2d 86 (Wyo. 1990); Wyoming Health Services, Inc. v. Deatherage,
773 P.2d 156 (Wyo. 1989); State Board of Equalization v. Jackson Hole Ski
Corporation, 745 P.2d 58 (Wyo. 1987); Brad Ragan Tire Company; Graham v. Wyoming
Peace Officer Standards and Training Commission, Wyo., 737 P.2d 1060 (1987);
Koontz v. Town of South Superior, 716 P.2d 358 (Wyo. 1986); Knudson v. Hilzer,
551 P.2d 680 (Wyo. 1976); Cranston v. Thomson, 530 P.2d 726 (Wyo. 1975); West v.
Willey, 453 P.2d 883 (Wyo. 1969). Cf. Reno Livestock Corp. v. Sun Oil Co.
(
It is neither
necessary nor proper for this Court to decide in this case whether or not we
will enforce a "no contest" clause if a challenged provision in a trust
agreement is in violation of the law. Although this question may properly be
before us in the future, an opinion rendered in this instance would clearly be
advisory. This Court has repeatedly said that it will not issue advisory
opinions, and we decline to do so now. Brad Ragan Tire Company v. Gearhart
Industries, 744 P.2d 1125, 1126 (
Briggs, 836
P.2d at 266.
[¶38.] Since this aspect of the court's opinion
is a classic example of an advisory opinion, it should not have been uttered,
and I feel compelled to disassociate myself from it. Other than this one
feature, I concur in the majority opinion.
URBIGKIT, Justice,
specially concurring.
[¶39.] I concur in the decision of the court
except for the segment regarding consequential damages in tort. I do not
understand the tort theory of malicious or improper intent failure to pay
construction payments when due to have been presented as a pleaded claim in the
initial pleadings or now to be presented as an appellate issue for this
litigation. Consequently, if this understanding of the state of our present
appellate record is correct, any present opinion discussion is dictum.1
[¶40.] I have a direct concern about any effort
to broaden the non-recovery of the consequential damage reach of Continental
Ins. v. Page Engineering Co., 783 P.2d 641 (Wyo. 1989), for which my dissent
remains unremitted.
[¶41.] The more encompassing concern is the
broad conclusion developed from any unlimited rule that delayed payments cannot,
in properly confined circumstances, create a tort liability. It is my perception
that the litigant can state a claim in tort if accompanied by proof of the
requisite malice or tortious ulterior purpose which extends damage beyond the
economics of purely delayed or denied payments, which would be, generally, the
value of the present payment of money. While there may be unusual and scattered
cases, the philosophic concept involving the tort of delay or non-payment, when
properly proved, addresses the same generic rationale as first-party or
third-party bad faith torts which we considered in McCullough v. Golden Rule
Ins. Co., 789 P.2d 855 (Wyo. 1990) (first-party) and in Western Casualty and
Surety Co. v. Fowler, 390 P.2d 602 (Wyo. 1964) (third-party bad faith failure to
settle).
[¶42.] Tortious conduct resulting from bad faith
failure to pay for ulterior purposes or malicious intent should not be excluded
from the arsenal of protection available to the wronged party by any assumptive
conclusions in this decision where the subject is not essentially presented by a
pending pleading, briefing or oral argument. I do not find the cited cases in
the majority decision of Bowdish v. Johns Creek Associates, 200 Ga. App. 93, 406
S.E.2d 502 (1991) and Preferred Marketing Associates Co. v. Hawkeye Nat. Life
Ins. Co., 452 N.W.2d 389 (Iowa 1990) to be counter-indicative. See, e.g., Woods
Petroleum Corp. v. Delhi Gas Pipeline Corp., 700 P.2d 1023 (Okla. App. 1983) and
the cases cited therein; Hall Jones Oil Corp. v. Claro, 459 P.2d 858 (Okla.
1969) and Oklahoma Natural Gas Co. v. Pack, 186 Okla. 330, 97 P.2d 768 (1939).
"It is well settled, however, that a tort may arise in the course of the
performance of a contract and that tort may then be the basis for recovery even
though it is the contract that creates the relationship between the parties."
Woods Petroleum Corp., 700 P.2d at 1027. For comparison, see Z.D. Howard Co. v.
Cartwright, 537 P.2d 345 (
[¶43.] The foundational concept authored in
dispositive fashion for bad faith insurance cases in Crisci v. Security Ins. Co.
of New Haven, Conn., 66 Cal.2d 425, 58 Cal.Rptr. 13, 18, 426 P.2d 173, 178
(1967) recognized:
Fundamental in our
jurisprudence is the principle that for every wrong there is a remedy and that
an injured party should be compensated for all damage proximately caused by the
wrongdoer. Although we recognize exceptions from these fundamental principles,
no departure should be sanctioned unless there is a strong necessity
therefor.
[¶44.] Consequently, I concur in this court's
decision, but would neither: foreclose for this case, if provident, proper or
within time limitation provided by statutes of limitation; nor, create for
future litigation, an absolute preclusion in this jurisdiction against the
injured party's alternative right to the remedies provided by the tort of
delayed payment based on particularized malice or ulterior purpose.
FOOTNOTES
1 The subject of
delayed payments was the basis for the thirty percent arbitration award which is
directly included as a subject in this appeal. The events, however, from which
that award flowed to now be reversed by this decision, occurred after the July
1987 date when this lawsuit was instituted and also after the
This non-payment by
justification of work deficiencies - when, in reality, the problem was shortage
of funds for payment - obviously bothered the neutral arbitrator. He said so and
assessed the thirty percent "surcharge."
This dispute, however, developed during arbitration long after the district court complaint and amended complaint had been filed and is not present, as far as I can discern, as a pending pleaded complaint stated in either tort or contract. The facts are not in much dispute and particularly so with finalization of the arbitration award defining basic amounts due from the owner to the contractor. The future potential for further pleadings, including a tort non-payment theory or its constituency criteria or legal effect, has neither been briefed nor argued during this appeal.